More than 200 days after expansion, Hedcor’s Ferdinand L. Singit  hydro power plant in Bakun, has delivered a total of 21 million kWh to date. The run-of-river hydro power plant was upgraded last year to increase its capacity to 6.15 MW from its previous 4.8 MW generation. This escalates the production of the plant to 9.3 million kWh annually. FLS Hydro is one of the three run-of river hydro power facilities operated by Hedcor in the municipality.